Ongrade Drainage & Excavation has been engaged by Your Section to deliver extensive civil and underground infrastructure works across multiple stages of the Falcons Run residential subdivision.
FALCON RUN SUBDIVISION, ROLLESTON
PROJECT OVERVIEW
Stages 1–5
- Comprehensive site clearance, including demolition and removal of existing dwellings, garages, farm structures, septic systems, boreholes, driveways, and associated services across the development footprint.
- Removal of hundreds of metres of existing trees, vegetation, and shelter belts, including stump removal and root raking to enable subdivision earthworks and infrastructure installation.
- Bulk earthworks exceeding 30,000m³ of topsoil stripping, including extensive cut to fill operations, engineered fill placement, and final shaping of residential lots, roads, and reserves.
- Installation of wastewater infrastructure including approximately 2,685m of sewer mains, comprising internal subdivision networks and significant off-site works along Lincoln Rolleston Road.
- Construction of approximately 1,200m of 100mm PVC sewer laterals, connecting residential lots and external tie-ins to the main sewer network.
- Installation of multiple benched manholes, including deep sewer installations, with full testing and commissioning.
- Construction of a comprehensive stormwater network including sumps, manholes, large-scale soakage pits, and associated pipework servicing staged residential development.
- Installation of potable water infrastructure including over 4,000m of water mains, together with property connections, valves, and associated fittings.
- Construction of internal roading including over 8,000m² of roading, multiple pavement layers, asphalt surfacing, and more than 1,500m of kerb and channel, along with footpaths, pedestrian crossings, and vehicle crossings.
- Significant external and interface works along Lincoln Rolleston Road, including road upgrades, drainage works, traffic management, and construction of a new roundabout providing primary access to the development.
Stages 6–10
- Further site clearance works including removal of remaining trees, shelter belts, and redundant farm infrastructure within subsequent development stages.
- Extension of wastewater infrastructure including approximately 900m of additional sewer mains and approximately 700m of sewer laterals, expanding the network to service later stages of the subdivision.
- Installation of additional manholes, testing, and connections to the existing wastewater network.
- Extension of potable water infrastructure including approximately 3,000m of additional water mains, property connections, and network fittings.
- Expansion of stormwater infrastructure including additional soakage systems, sumps, and manholes integrated into the wider subdivision network.
- Construction of additional internal roading, kerb and channel, footpaths, and vehicle crossings to support the staged release of further residential lots.
- Completion of all testing, as-built documentation, and compliance works in accordance with local authority requirements.
CONTACT US
